Complete electrical package for a 1.2-million-square-foot fulfillment center — one of Nickle's largest single-site projects. Scope included medium-voltage distribution from dual utility feeds, high-bay LED lighting across all pick modules and sortation areas, conveyor power feeds serving thousands of motor connection points, and a 3,000 kW emergency generator system with automatic transfer switches. The project was delivered on an aggressive 14-month schedule requiring peak manpower of 180+ electricians.